Admin Building Parking Lot Restoration

Hernando County B.O.C.C. | 15470 Flight Path Dr, Brooksville, FL 34604 | Contract 25-C01185/GB | Schedule Rev B · Confirmed
Mobilization
Fri Aug 21
FF mobilization to site
Work Begins
Mon Aug 24
Concrete work — early starts, low noise
Program Length
5 Weeks
Aug 21 → Sep 21 · All Dates Confirmed
Work Phases
5
Mob+Concrete → Asphalt → Prep → Lot C+Polyguard → Closeout
Final Walk
Mon Sep 21
With Sam & team
Overall Progress
0%

Project Owner

Hernando County BOCC
  • Sam Burdin — Primary Project Contact, Hernando County Facilities
  • 15470 Flight Path Dr, Brooksville, FL 34604
  • Office (352) 540-6574 · Fax (352) 540-4348
  • sburdin@co.hernando.fl.us
  • Final walk-through Mon Sep 21 with Sam & team

Contractor

Firm Foundations Asphalt & Concrete LLC
  • Arthur Wilmoth — CEO / President
  • Joe Santerelli — Project Manager (Primary On-Site)
  • 10701 N Nebraska Ave, Tampa, FL 33612
  • 813-853-6597 | CBC1267421

Project Scope Summary

5 Confirmed Phases · Aug 21 → Sep 21, 2026
  • Phase 1 — Mobilization & Concrete Work (Fri Aug 21 → Thu Aug 27): FF mobilizes to site Fri 8/21; concrete work Mon–Wed 8/24–26 with early starts to keep noise down; forming inspection Tue 8/25 (tentative); finish-pour inspection Thu 8/27.
  • Phase 2 — Asphalt Removal & Crack Repair (Mon Aug 31 → Fri Sep 4): Lot A asphalt removal Mon night 8/31 into Tue 9/1 (night work); concrete crack fill Wed–Fri 9/2–4 (day or night TBD).
  • Phase 3 — Final Concrete Prep (Tue Sep 8): final lot concrete prep work, if any is needed — single day.
  • Phase 4 — Lot C Milling, Paving & Polyguard (Tue Sep 15 → Fri Sep 18): Lot C milling / base work / grubbing Tue 9/15 (day); Lot C paving Wed 9/16 (day — noisy); Polyguard installation and paving Thu night 9/17 into Fri 9/18 (night work).
  • Phase 5 — Wheel Stops, Striping & Closeout (Sat Sep 19 → Mon Sep 21): lot closed Sat–Sun 9/19–20 for wheel stop installation + pavement marking of all 3 lots; final walk with Sam & team Mon 9/21.
  • FFAC provides for project duration: MOT / traffic control, light tower, port-o-let with handwash & eyewash station.

Key Dates & Permits

Contract Terms · Rev B · Confirmed Schedule
  • Contract number: 25-C01185/GB
  • Mobilization: Fri Aug 21 — FF equipment & staging on site
  • Concrete work: Mon–Wed Aug 24–26 (early starts, low noise)
  • Forming inspection: Tue Aug 25 (tentative, coordinated with County)
  • Finish-pour inspection: Thu Aug 27
  • Lot A asphalt removal: Mon night Aug 31 → Tue Sep 1 (night work)
  • Polyguard install + paving: Thu night Sep 17 → Fri Sep 18 (night work)
  • Lot closed Sat–Sun Sep 19–20 for wheel stops + striping across all 3 lots
  • Final walk-through: Mon Sep 21 with Sam & team
  • Performance & Payment Bond on file · FDOT specs for asphalt & tack coat
  • Schedule excludes weather delays; dates adjusted with notice to County

Site Inspection & Coordination

On-Site Contacts
  • Hernando County BOCC representative — daily coordination; primary contact Sam Burdin (see Project Owner card)
  • Active county facility — phased work to maintain operations at all times; building access preserved throughout
  • Front parking areas will be partially coned during Phase 1 concrete phase for pedestrian & vehicle safety
  • Laydown / staging in the designated grassy area behind the building
  • Crew access route via main entrance drive — no impact to visitor / staff parking during business hours
  • Weekly progress email to County with the coming week's closures & work zones (Fri afternoons)
Daily documentation (sign-in sheets, Toolbox Talks, SWPPP inspections) is captured under “Across Every Phase” on the Scope of Work tab.

MOT & Safety

Active County Facility
  • Phase 1 concrete work: Mon–Wed Aug 24–26 · early daytime starts to minimize noise near building operations
  • Phase 2 Lot A asphalt removal: Mon night Aug 31 into Tue Sep 1 — NIGHT work to keep the lot open days
  • Phase 2 crack fill: Wed–Fri Sep 2–4 — day or night, to be confirmed with County
  • Phase 4 Lot C milling: DAYTIME — Tue Sep 15
  • Phase 4 Lot C paving: DAYTIME — Wed Sep 16 (noisy day — County notified in advance)
  • Phase 4 Polyguard install + paving: NIGHT — Thu Sep 17 into Fri Sep 18
  • Phase 5 wheel stops + striping: Sat–Sun Sep 19–20 — lot fully closed both days (all 3 lots)
  • Cones & barriers mark all work zones; phased lot closures
  • Full PPE (hardhats, hi-vis vests w/ FF logo, safety boots)
  • Spotters, backup alarms, OSHA-compliant operations
  • Daily site cleanup; drive lanes restored end of shift
  • Public access maintained to remaining open lots throughout

Official Schedule & Work Calendar

Rev B · Confirmed Schedule (Aug 21 → Sep 21, 2026)
  • The one-page project schedule with a day-by-day Gantt is provided as the primary source-of-truth document below.
  • Rev B is the confirmed schedule. All dates in this dashboard match the PDF; if there is any conflict, the PDF governs.
  • Any future date change will re-issue as Rev C and this dashboard will update alongside it.
📄 Project Schedule (Rev B · Confirmed) · PDF 📄 Rev A (superseded) · PDF

Scope of Work — Rev B Phase Breakdown (Confirmed)

Sequenced per the confirmed FFAC schedule (Rev B). Five phases, Aug 21 → Sep 21, 2026. Mobilization & concrete work first with early daytime starts to keep noise down; asphalt removal and crack repair second; a single-day concrete prep window; then Lot C milling / paving / Polyguard; and finally a lot-closed weekend for wheel stops & striping across all 3 lots, capped by the final walk-through with Sam and team. Schedule excludes weather delays.

Phase 1 — Mobilization & Concrete Work

Fri Aug 21 → Thu Aug 27 · FFAC
  • Fri Aug 21: FFAC mobilization to site — equipment, staging setup, MOT devices & port-o-let / handwash station in place
  • Mon–Wed Aug 24–26: Concrete work — crews start as early as possible each day to minimize noise near County business hours
  • Tue Aug 25: Forming inspection (tentative — coordinated with County)
  • Thu Aug 27: Finish-pour inspection
  • SWPPP (silt fence, inlet protection) verified in place before soil disturbance
Duration: 5 work days incl. mob · Sets the concrete base for the asphalt phases that follow

Phase 2 — Asphalt Removal & Crack Repair

Mon Aug 31 → Fri Sep 4 · FFAC
  • Mon night Aug 31 → Tue Sep 1: Lot A asphalt removal — NIGHT work to keep the lot open during County business hours
  • Wed–Fri Sep 2–4: Concrete crack fill — day or night, to be confirmed with the County
  • All work zones cordoned; spotters + backup alarms; drive lanes restored end of each shift
  • Continued daily SWPPP inspections
Duration: 5 days (1 night + 3 flex) · Night-work windows subject to County confirmation

Phase 3 — Final Concrete Prep

Tue Sep 8 · FFAC (single day)
  • Tue Sep 8: FFAC returns to site for any final lot concrete prep work identified during Phase 1 forming/finish inspections or Phase 2 crack fill
  • If no additional concrete prep is needed, this phase is skipped and the schedule slides forward accordingly
  • Buffer week (Sep 9–12) between Phase 3 and Phase 4 allows cure + weather window before Lot C paving
Duration: 1 day (contingent) · Absorbs any concrete carry-over before we commit to Lot C

Phase 4 — Lot C Milling, Paving & Polyguard

Tue Sep 15 → Fri Sep 18 · FFAC (day + night mix)
  • Tue Sep 15 (DAY): Lot C milling of existing surface + base work + selective grubbing
  • Wed Sep 16 (DAY — NOISY): Lot C paving — County notified in advance so tenants can plan around the noise window
  • Thu night Sep 17 → Fri Sep 18 (NIGHT): Polyguard membrane installation and paving — night work to keep the lot usable during business hours
  • Rolling & compaction per FDOT spec — breakdown / intermediate / finish rollers
  • Cure time before opening to traffic
Duration: 4 work days · Polyguard was re-added to this scope per confirmed Rev B (was previously deferred)

Phase 5 — Wheel Stops, Striping & Closeout

Sat Sep 19 → Mon Sep 21 · FFAC + Final Walk
  • Sat–Sun Sep 19–20 — LOT CLOSED (weekend): Wheel stop installation + pavement marking across all 3 lots (A, B, C) — requires the full lot closure so paint can cure without traffic
  • Mon Sep 21: Final walk-through with Sam & the team
  • SWPPP take-down (silt fence, inlet protection)
  • Site cleanup, demobilization, as-built submission
Duration: 3 days · Wheel stops were re-added per confirmed Rev B; the lot-closed weekend is the tradeoff for a clean, cured stripe job

Across Every Phase

Continuous Requirements
  • FFAC provides for project duration: MOT / traffic control, light tower, port-o-let with handwash & eyewash station
  • Full PPE (hardhats, hi-vis vests w/ FF logo, safety boots)
  • Daily site cleanup; drive lanes restored end of shift
  • Building access maintained at all times except the Sat–Sun Sep 19–20 lot-closed weekend
  • Daily sign-in sheets posted at staging area
  • Weekly Toolbox Talks & SWPPP inspections
  • Weather delays: schedule adjusts with notice to Sam & the County
Governing document: FFAC Project Schedule Rev B · Confirmed (linked on Overview)

Project Schedule — Rev B (Confirmed)

📅
Rev B · CONFIRMED — Mobilization Fri Aug 21 · Final Walk with Sam & Team Mon Sep 21
All dates in this schedule are confirmed. Concrete work Mon–Wed Aug 24–26 uses early daytime starts to minimize noise. Lot A asphalt removal is NIGHT work Mon 8/31 → Tue 9/1. Lot C paving day Wed 9/16 will be noisy; Polyguard install night Thu 9/17 → Fri 9/18. Lot fully closed Sat–Sun Sep 19–20 for wheel stops + striping across all 3 lots. » Download official Rev B schedule PDF
Mobilization
Fri 8/21
Equipment + staging on site
Concrete Work
Mon 8/24
Early starts, low noise
Lot A Removal
Mon 8/31 night
Night work → Tue 9/1
Polyguard Install
Thu 9/17 night
Night work → Fri 9/18
Final Walk
Mon 9/21
With Sam & team
Task Wk of Aug 17 Wk of Aug 24 Wk of Aug 31 Wk of Sep 7 Wk of Sep 14
Mob (Fri 8/21) Phase 1 Concrete Phase 2 Asphalt Phase 3 (Sep 8) Phases 4 + 5
PHASE 1 — MOBILIZATION & CONCRETE WORK
Mobilization — equipment + staging (Fri 8/21)
Concrete work — early starts (Mon–Wed 8/24–26)
Forming inspection — tentative (Tue 8/25)
Finish-pour inspection (Thu 8/27)
PHASE 2 — ASPHALT REMOVAL & CRACK REPAIR
Lot A asphalt removal (NIGHT, Mon 8/31 → Tue 9/1)
Concrete crack fill (Wed–Fri 9/2–4, day or night TBD)
PHASE 3 — FINAL CONCRETE PREP
Final lot concrete prep, if needed (Tue Sep 8)
PHASE 4 — LOT C MILLING, PAVING & POLYGUARD
Lot C milling + base work + grubbing (DAY, Tue 9/15)
Lot C paving (DAY — noisy, Wed 9/16)
Polyguard install + paving (NIGHT, Thu 9/17 → Fri 9/18)
PHASE 5 — WHEEL STOPS, STRIPING & CLOSEOUT
Wheel stops + striping — ALL 3 LOTS (LOT CLOSED, Sat–Sun 9/19–20)
Final walk with Sam & team (Mon 9/21)
Concrete Work
Paving / Polyguard
Asphalt Removal (Night)
Crack Fill / Repair
Milling / Base / Grubbing
Wheel Stops + Striping (Lot Closed)
Inspection / Final Walk
Mobilization

Photo Timeline

Before, during, and after documentation. Admin can upload photos from the Admin panel.

📷

No photos yet

Photos will appear here as the project progresses.

Project Documents

Documents are filed in a folder tree — Master Templates at the top (blank forms), then Week 1–6 matched to the Rev A schedule dates, each with Sun–Sat sub-buckets. Weekly certified payroll, sign-in sheets, safety meetings, SWPPP inspections, permits, insurance certificates, and RFI responses all live here.

The chips below filter by category across every folder in the tree.

📂

No documents yet

Master templates go in the top folder. Once construction starts, file each daily doc under Week N → day-of-week.

Project Progress

Overall Completion0%
Phase 1 — Mob & Concrete Work
0%
Phase 2 — Asphalt Removal & Crack Repair
0%
Phase 3 — Final Concrete Prep
0%
Phase 4 — Lot C Mill / Pave / Polyguard
0%
Phase 5 — Wheel Stops / Striping / Closeout
0%
🚧

No updates yet

Progress updates will appear here once the project begins.

Field Notes

Observations, issues, RFIs, daily logs — added during construction via the Admin panel.

📝

No field notes yet

Admin Panel

Post Progress Update

📷

Click or drag photos here

📂 Upload Document

Daily sign-in sheets, safety meeting notes, SWPPP inspection reports. PDFs preferred; PNG/JPG/DOC also accepted.

📂

Click or drag file here (PDF, image, or Office doc)

🗂 Manage Documents

View or delete uploaded documents.

No documents uploaded yet.

📷 Upload Photos

Up to 5 photos at a time. Auto-compressed for fast upload from phone.

📈 Update Progress

📝 Add Field Note

📝 Manage Field Notes

No field notes yet.

🗒 Manage Updates

No updates posted yet.

Admin Access

← Back to Dashboard